Friday, December 7, 2012
New Labels for Waste Receptacles- Help Make CI Sustainable
OP&C is committed to making CI a more sustainable campus. In an effort to promote recycling, OP&C will be labeling various trash receptacles around the campus. The labels will be pasted directly onto the receptacles, including old trash can containers, dining area containers, etc.
Burgess Courtyard Conversion
Operations, Grounds and PD&C have been reconfiguring the existing parking lot, previously known as the A9 Lot, into a landscaped courtyard. Concrete and final grade work have been completed and the Grounds staff has completed planting. The Grand Opening Ceremony is scheduled for December 7, 2012.
Before |
After |
Thursday, December 6, 2012
Campus Moves Continue
Del Norte Hall 3rd Floor Renovation Plans
Del Norte Hall 3rd Floor renovations are set to begin. This space was initially built to be office spaces, however, it will be converted into new classrooms and seminar rooms. The project will begin on December 17th, 2012 and is scheduled for completion in early April of 2013.
New Del Norte Building |
Wednesday, November 21, 2012
Campus Back Up Power
Burgess Courtyard Conversion
Thursday, November 8, 2012
Finance & Budget Move
New Mail Services Procedure
Mail Services is now offering Interoffice Special Delivery as a new service for the Campus. This can include, but is not limited to, the transfer of money, sensitive documents and special items that need to be delivered sooner than the normal twice a day delivery.
Please call the Mail Services Department at Extension 8927 if you wish to have something delivered which needs special handling.
Please call the Mail Services Department at Extension 8927 if you wish to have something delivered which needs special handling.
Mail Services Student Assistant, Jenny Arevalo |
Central Mall Conversion- Grounds
Reclaimed Water Line Installation
Monday, October 29, 2012
Green House
OP&C staff is installing a new greenhouse for the Science Department which is located adjacent to Modoc Hall. This project was put on hold to close out the current year-one grant money. On October 1st, construction started on the second phase of the year-two grant money.
The Greehouse Lighting has been Installed |
North Quad Building Refresh
Grand Salon Interior Refresh
OP&C staff have upgraded the lighting, installed carpeting, refreshed the Heating, Ventilation and the Air-Conditioning (HVAC) system, repainted the interior and exterior walls, installed window coverings and coordinated the installation of sound panels. This project is complete and some minor punch list items will occur over the next few weeks.
Grand Salon Interior Refresh |
Central Mall Conversion- Planting
OP&C staff is currently installing new irrigation lines in the Central Mall. After the irrigation installations are completed, planting of native, drought tolerant plants will occur. Saturday, October 27th marks the first date for volunteers to join our staff in planting on the Central Mall. For more information regarding volunteer services for this project, please contact OP&C at (805) 437-8461.
Achillea Millefolia 'Common Yarrow' |
Central Mall Peace Pole
OP&C staff have completed the installation of the Peace Pole, including installation of the sod and irrigation system at the two center lawn areas located within the Central Mall. Irrigation is complete in front of Ojai Hall down to the driveway at the Bell Tower East Courtyard.
Peace Pole
Department of Finance Move
Friday, September 21, 2012
Central Mall Conversion
Operations, Grounds, and PDC are reconfiguring the existing mall into a pedestrian friendly space where the roadways will be replaced with decomposed granite paths. New planters and landscaping will be installed and the street lighting will be upgraded.
The Grounds staff installing the irrigation lines |
Bell Tower HVAC Sound Attenuation
OPC staff is in the process of installing sound attenuators within the Bell Tower HVAC duct work to reduce noise levels caused by air blowing through the system. This work is focused in the second floor of the south hallways in the Bell Tower Core and is being done off hours. This project is now completed, several punch list items will occur over the next week.
North Quad-Grand Salon Refresh
A9 Lot Conversion
Wednesday, September 12, 2012
Campus Back Up Power
El Dorado Hall Roof Replacement
The existing roof in El Dorado Hall had gone beyond its life expectancy. It has been replaced with a new 30 year roof system that offers the benefits of a cold tar system while providing 6 LEED points and pursuing the environmentally friendly strategy the 'Green Campus' strives to follow.
El Dorado Hall new roof |
Friday, September 7, 2012
A9 Lot Conversion
North Campus Parking Lot
Enrollment is growing at CSUCI and many of us feel the stress of trying to find a parking spot on campus. The North Campus Parking Lot is completed and ready for use. This lot will help relieve some of the parking stress. There are 300 new spaces in this lot. A pedestrian walkway and bridge connect the lot to Ventura St by El Dorado Hall.
North Campus Lot in Use |
Thursday, September 6, 2012
Central Mall Renovation
The hard scape work of this project is nearing complete. Decomposed granite walkways will be installed shortly and irrigation and planting work will follow. The decomposed granite walkways have high porosity. This means that water can penetrate the soil easily creating less puddles and poolings so we all can get to class and work on time and mess free!
Central Mall, Under Construction |
El Dorado Main Electrical Panel Upgrade
CI Park Safety Upgrades
Wednesday, September 5, 2012
Broome Fountain Repair
Friday, August 24, 2012
Central Mall and A-9 Lot
Los Angeles Avenue is being converted into a Central Mall. When complete, the Central Mall will be open to pedestrian traffic only (except for emergency and maintenance vehicles), and will provide outdoor gathering spaces for the community. The landscaping along the Mall will also be upgraded. This is primarily a donor-funded project. Barring unforeseen circumstances, we plan to open the Mall by September 15th. Irrigation and landscaping work will continue into October. The Campus is planning a "Planting Day" when the entire campus community will be invited to participate in planting the new landscaping along the mall. Announcements will be sent soon.
Central Mall Conversion |
The Parking Lot A-9 is also closed and will be converted into a landscaped courtyard. This is also a donor-funded project. The theme of this courtyard is sensory. Gathering spaces will be created in a fragrant and colorful environment.
A-9 Conversion |
Del Norte and Madera Halls
To serve a growing campus, two new buildings, Del Norte and Madera, have been added to the Campus. These buildings were completed during the summer. The buildings will anchor the development of the North Quad area. Third floor construction will continue in the Fall semester and additional classrooms will be built. The North Quad landscaping is in progress and hydro-seeding is planned next week. We are also refreshing the exteriors of adjacent buildings in the North Quad area.
You will notice some construction activities inside the building as "punch list" work is still in progress. As with any new buildings, certain systems will not work as planned or may even fail. Please notify OPC Work Center immediately (opcworkcenter@csuci.edu or ext. 8461). We will attempt to correct the problem as soon as possible.
North Quad |
Del Norte |
New Road and Parking Lot
The new University Drive is open, and Camarillo Street has been re-paved. A new 300 space parking lot will alleviate parking problems. The new parking lot begins the process of moving parking to the north side of the campus, and makes the campus pedestrian and bicycle-friendly. The landscaping for the parking lot will be completed towards the end of this year.
North Campus Lot |
Wednesday, August 22, 2012
Class Rooms
LA Avenue
Monday, August 20, 2012
Friday, August 17, 2012
Placer Hall Exterior Refresh- South Side
Long Grade Creek
Restoration
The grounds department is in the process of restoring Long Grade Creek near the Entrance Road. They are preforming weekly weed abatement and planting native plants.
Parking Lot A9
Wednesday, August 15, 2012
North Parking Lot
Aerial View of the Parking Lot Under Construction |
The new surface lot will include approximately 535 permanent parking spaces on undeveloped land adjacent to the recently opened Entrance Road. The scope includes new paving, energy efficient, dark sky lighting, emergency telephones, and drought- tolerant landscaping with natural bio-swales to manage storm water runoff. Contractors are currently placing curbs and gutters and will begin fine grading in preparation of paving.
Parking Lines Placed |
Tuesday, August 14, 2012
Boating Instruction and Safety Center: "BISC"
BISC Rendering |
Currently, contractors have completed the framing, the installation of mechanical, electrical and plumbing work, and are working on drywall operations. Exterior siding and plaster work is complete and finish work will continue through the coming months. The construction and installation of a new boat is also beginning soon.
BISC Construction |
El Dorado Hall Roof